路径:Controlling --> Internal Orders --> Settlement --> Maintain Allocation Structures
设置A1-->Settlement Cost Element
如果把 By cost element 的勾勾上,表示订单结算时以订单当前的成本要素进行结算,相当于分配,
但是勾上时报错,提示:
这个是什么意思,如果解决??
Specify original cost element ('OCE'), or enter a settlement cost element
Message no. K4013
Diagnosis
You must either activate the switch 'Settlement by original cost element' ('OCE') or enter a settlement cost element. You cannot do both at the same time.
In settlement by cost element, the debit cost element is the same as the credit cost element.
If you are using settlement cost elements, the type you enter depends on the receiver type
cost element type 21 for internal settlement
cost element type 22 for external settlement
Procedure
Switch on the function 'settlement by original cost element' ('OCE').
or
Select a cost element of type 21 or 22 using the F4 function.
or
Create a cost element of type 21 or 22.
其实楼主只是没看清楚